Time line information
Stage 1: 2007
| Late 2006 | Initial proposals and ideas developed |
| February – March 2007 | Consultation events |
| March 2007 | Proposals finalised |
| March 2007 | HLF Stage 1 submission |
| March – September 2007 | Proposals revisited and further information supplied to HLF |
| March 2008 | Heritage Lottery Fund (HLF) Stage 1 Bid approved for Stage 2 Development Funding |
Stage 2: July 2008 - September 2009 - Project Delivery
| July 2008 | Work commences on developing stage 1 Proposals |
| November 2008 | Illuminations Consultation Event |
| December and January 2008/09 | Proposals refined and detailed |
| February / March 2009 | Consultation Events |
| September 2009 | HLF Stage 2 Submission – Stage 2 bid submitted |
| March / April 2010 | HLF Decision announced (Anticipated date) |
| 2010 | Works start on site (Anticipated date) |
| Late 2011 / early 2012 | Visitor Centre opened (Anticipated date) |
| 2013 | Work completed (Anticipated date) |